HVDC TRANSMISSION LINE

▒660KV HVDC Transmission Line Project

HVDC TRANSMISSION LINE

Total Project Cost û US$ 1658.34 Million

Barqaab Share û 70% (Local Component)

Date of Commencement û March 2018

Date of Completion û February 2021

Scope of the Project

HVDC 660 kV Bipole Transmission Line approximately 870km from Matiari to Lahore
HVDC Converter Station, Lahore
HVDC Converter Station, Matiari
Three Repeater Stations
Grounding electrodes and Electrodes Lines at Matiari and Lahore.

Scope of Services

System Studies, Contract Assistance, Design Review, Construction Support, Quality Assurance, Operation & Maintenance, Training & Technology Transfer and Construction Supervision.